Getting a home EV charger fitted is usually straightforward — but knowing the steps helps you prepare and spot a good installer from a rushed one. Here’s the process from first enquiry to charging your car.
Step 1: The site survey
A good installer assesses your property before quoting — often with photos or a visit. They’re checking:
- Where your consumer unit and incoming supply are, and their capacity
- Where you park and the best charger position
- The cable route from board to charger, and its length
- Whether your fuse board has a spare way and adequate main fuse
- Earthing arrangements (modern chargers handle this, but it’s checked)
This survey is what lets them give an accurate price — be wary of a fixed quote with no survey.
Step 2: The quote and charger choice
You’ll choose a charger (tethered vs untethered, 7kW being standard for homes — see our 7kW vs 22kW guide) and get a quote covering the unit, the dedicated circuit, the cable run, and any board work. If you qualify for the grant (renters/flat owners/landlords), the installer applies and deducts it — see our OZEV grant guide.
Step 3: DNO notification
Home chargers must be notified to your DNO (the network operator). For a standard 7kW install this is usually a straightforward post-installation notification the installer handles. Larger installs (22kW) may need DNO approval first, which can add lead time. Either way, a proper installer manages this — you don’t have to.
Step 4: Installation day
A typical 7kW home install takes half a day to a day. The installer will:
- Run a dedicated circuit from your consumer unit
- Fit any necessary board protection (or upgrade the board if needed)
- Mount the charge point and route the cable tidily
- Test the installation and commission the charger
- Show you how to use it and any app
What can affect the timeline or cost
- Cable run length — a charger far from the board means more cable and labour
- Board capacity — a full or outdated board may need upgrading first
- Groundworks — trenching across a driveway adds time
- Supply upgrades — occasionally the main fuse or supply needs the DNO involved
- Property type — flats and no-driveway homes need more assessment
Step 5: Certification
You should receive certification for the electrical work (it’s a new circuit, so it’s notifiable under Part P). Keep it — it matters for warranties, insurance, and selling the home.
What good looks like
- A proper site survey before quoting
- A dedicated, correctly protected circuit to BS 7671
- DNO notification handled for you
- A tidy, well-positioned charge point
- Certification provided
- The grant applied if you’re eligible
How to prepare
- Decide where you’d like the charger (near where you park, ideally close to the board)
- Clear access to your consumer unit
- Have your vehicle details handy (for grant eligibility and charger choice)
- Mention any plans for future loads (heat pump, battery) so capacity is considered